Sibelco Project Completion
PT. Lintech Duta Pratama - April 18,2019
Lime Plant Padalarang - Sibelco Completion
- Project Name: Lime Plant Padalarang - Sibelco
- Capacity: 400 Ton/Day
- Steel Fabrication and Erection: 5000 Ton
- Electrical Power, Design, Supllay, Install, Programming and Commissioning: 10 MWatt
- Mechanical Equipment Installation: 2000 ton
- Commisioning Date: 27 December 2016
Again, Lintech has proven high safety and quality standard on our EPC project.
Lintech has achieved 1 million manhours without accident on 85% completing lime plant project.
Congratulation to Lintech for completing world class plant and Sibelco for the brand new quality asset.